What are stem wall and grade beam foundations?
In short: A stem wall foundation is a short wall built on a continuous footing, used under crawl spaces, on sloped lots and around some slabs. A grade beam foundation is a concrete beam spanning between drilled piers that reach below the clay that swells and shrinks, with a gap under the beam so the clay cannot lift it. Both can move in Oklahoma clay, but for different reasons.
What is a stem wall on a footing?
A footing is the wide concrete base that spreads the house's weight onto the soil. A stem wall is the vertical wall of concrete or masonry that rises from it.
- Footing size: code minimum 12 in wide and 6 in thick, with larger sizes from the code tables for heavier loads 1.
- Footing depth: at least 12 in below the ground surface, and below the frost line where frost applies 1.
- Sloped lots: footing bottoms may slope up to 10%; steeper ground requires stepped footings with level tops 1.
- Reinforcement where the code's seismic provisions apply: vertical No. 4 bars at no more than 4 ft, hooked into the footing and extending at least 14 in into the wall, plus a horizontal No. 4 bar within 12 in of the top 2.
- Oklahoma additions: the state's 2024 code adoption adds two No. 4 bars to all footings and requires cold joints between footing and stem wall to be tied with No. 4 bars at each corner, no more than 6 ft apart, with 12 in of embedment 3.
- Anchor bolts: at least 1/2 in diameter, no more than 6 ft apart and embedded at least 7 in, tying the wood sill to the wall 4.
A cold joint is the seam where concrete poured on one day meets concrete poured later, such as a stem wall cast on a footing that has already set.
What is a grade beam on drilled piers?
A drilled pier is a concrete column cast in an augered hole. A grade beam is a reinforced concrete beam that spans from pier to pier at the ground surface and carries the walls.
Engineering guidance for swelling soils describes this system as the general choice for moderately to highly swelling soils 5:
- Piers extend well below the zone of seasonal moisture change 5.
- Piers are anchored in non-swelling soil to resist uplift, by belled bottoms, grooved holes or extra depth 5.
- A gap of 3 to 6 in is left between the soil and the grade beam so swelling soil cannot push up on it 5. Cardboard void forms that hold this space during the pour are commonly called void boxes.
Drilled piers have been used for houses on expansive soil in California, Colorado and Texas since the late 1950s 7. Seasonal moisture change can extend from 3 to 40 ft deep, and the upper part of a pier can lose contact with the soil as clay shrinks 7.
How do these foundations fail?
| Problem | What happens | Source |
|---|---|---|
| Void space missing or too small | Swelling clay pushes directly on the grade beam | 6 |
| Piers too short or wrong diameter | Pier rides up and down with the clay | 67 |
| Mushroom-topped piers | Listed as a construction defect behind swelling-soil damage | 6 |
| Corner piers lifting | Wet-season swell lifts corners; dry-season shrink can let them drop | 7 |
| Long drought then a wet year | Six-foot piers that handle normal years can fail | 7 |
| Stem wall on shallow footing | Footing moves with the active zone like any shallow foundation | 7 |
When piers move after construction or repair, the mechanism is covered in pier uplift or movement after repair. Underpinning brackets bear on the stem wall or grade beam itself; spacing and load questions are covered in loads, pier spacing and capacity.
How are these foundations repaired?
- Deeper or belled supports: drilled bell-bottom piers
- Steel underpinning on the stem wall: steel push piers or helical piers
- Moisture control around the perimeter: drainage and root barriers
- Mixed foundations where an addition meets the original house: additions and mixed foundations
Related
- Drilled Bell-Bottom Piers
- Pier and Beam Crawl Space
- Pier Uplift or Movement After Repair
- Loads Pier Spacing and Capacity
- Shrink-Swell and Active Zone
Common questions
What is a stem wall foundation?
A stem wall is a short concrete or masonry wall built on a continuous footing. It raises the house above grade and either carries a wood floor over a crawl space or surrounds a slab poured inside it.
What is a grade beam on drilled piers?
It is a reinforced concrete beam that spans between drilled concrete piers. The piers carry the load down below the zone of seasonal soil moisture change, and on swelling soils a gap is left under the beam so the clay cannot push it up.
Why would a grade beam foundation heave?
Common causes named in engineering guidance include a missing or inadequate void space under the beam, piers that are too short or the wrong diameter, and mushroom-topped piers.
What reinforcement does Oklahoma require in footings?
Oklahoma's adoption of the 2024 International Residential Code adds two No. 4 bars to all footings and requires cold joints between footings and stem walls to be tied with No. 4 bars at each corner and no more than 6 feet apart.
Sources
- Inspecting Footings: The Unsung Heroes Beneath a House (IRC R403) InterNACHI
- Steel Bones: Inspecting the Critical Role of Rebar in Foundation Strength (IRC R403.1-R403.1.6) InterNACHI
- Adoption of International Residential Code 2024 (IRC 2024) Oklahoma Uniform Building Code Commission
- Securing the Perimeter: Inspecting Foundation Anchor Bolts and Sill Plate Protocols (IRC R403.1.6) InterNACHI
- Home Construction on Shrinking and Swelling Soils (Special Publication 11) Colorado Geological Survey (Holtz and Hart, 1978)
- Expansive Soil Colorado Geological Survey
- Damage to Foundations from Expansive Soils Missouri University of Science and Technology (J. David Rogers, Robert Olshansky, Robert B. Rogers)
Was this page helpful?