How is foundation movement monitored in Oklahoma?

Reviewed by Preston, Oklahoma foundation repair consultant · Updated 2026-10-14

In short: A monitoring program measures a foundation repeatedly over months to learn whether it is still moving, which direction it is moving, and whether the movement follows the seasons. Engineering guidelines call for at least a year of readings, because repairs made after movement has stopped are less likely to see distress return 1. In Oklahoma's expansive clays, monitoring is often the first step when a slab may be heaving rather than settling.

What is a monitoring program?

Monitoring is observation, not a repair. It combines three kinds of records taken on a schedule:

The goal set out in engineering guidance is to determine whether excessive movement is happening, whether it has likely stopped, and why it happened 1.

Why does monitoring matter on Oklahoma clay?

Expansive clay swells when wet and shrinks when dry. The depth where this seasonal moisture change happens is called the active zone. A study using Oklahoma Mesonet field data estimated active zone depths across the state at roughly 0.5 to 4 meters (about 1.5 to 13 feet), with shallower soil reacting most to weather 7.

Because the soil moves up and down with the seasons, a single visit can mislead. A slab edge that looks low in a dry August may rise again after spring rain. Monitoring separates two patterns 1:

Pattern seen over time What it suggests
Points rise and fall in step with seasonal rainfall Cyclical movement, typical of expansive soil
Points trend steadily in one direction Non-cyclical movement that has not stabilized
Cracks reopen in the same place after repair Continuing movement rather than seasonal cycling

This is why monitoring is often the first step for perimeter wetting heave, post-tree-removal heave and leak-related heave: the soil may need time to reach moisture balance before anyone can tell what, if anything, needs lifting. See heave vs settlement for how the two are told apart.

How are the measurements taken?

Elevation surveys

More on the method is in elevation surveys.

Crack monitoring

Simple gauges show whether a crack is still active. Federal preservation guidance describes three approaches: two pencil marks on tape across the crack measured on a schedule, a glass slide epoxied across the crack that breaks if movement continues, and a two-plate sliding crack monitor with a printed scale 3. Measurements are charted at regular intervals and kept on file with photographs 3. Seasonal opening and closing is covered in cracks that open and close seasonally.

Soil moisture records

The Oklahoma Mesonet reports soil moisture at most of its stations at depths of 2, 4, 10 and 24 inches 4. Its Fractional Water Index runs from 0 (near the wilting point, very dry) to 1 (near field capacity, wet) 4. The Mesonet website publishes daily values and graphs of recent readings 45. Recording the nearest station and its reading with each survey lets a later reader see whether the soil was wet or dry at the time. See Mesonet for foundation pros.

How often are readings taken and when is movement stable?

Guidelines from a Texas engineering group working on similar expansive clays set out these points 1:

The same guidelines treat movement as generally stabilized when the largest differential change is about 0.3 inch or less over three to four months (0.4 inch or less over six to eight months), no new functional or structural distress appears, and the movement lines up with climate and rainfall 1. The authors note the guidance was written for Southeast Texas and should be applied with care elsewhere 1.

For ongoing homeowner checks, a companion guide suggests inspecting the site and structure twice a year and after extreme wet or dry weather, comparing results with earlier photos and records 6.

What are the limitations of monitoring?

Free, plain-English answers. It asks a few questions and walks you to the repair that fits.

Common questions

How long should a foundation be monitored before deciding on repair?

Engineering guidelines call for at least one year of monitoring, with at least three elevation surveys and the first and last taken in the same season, so seasonal swings can be separated from ongoing movement.

Can I use a carpenter's level to check my floors over time?

No. Published guidelines say a spirit or carpenter's level is not accurate enough for an elevation survey; a manometer-style or other floor-level instrument reading to about 1/8 inch is used instead.

What does it mean if a crack closes in spring and opens again in summer?

A crack that opens and closes with the seasons is moving with soil moisture. It indicates cyclical movement, which is typical of expansive clay, not that the problem fixed itself.

How can I check soil moisture conditions where I live in Oklahoma?

The Oklahoma Mesonet publishes daily soil moisture readings at depths from 2 to 24 inches at most of its stations, including the Fractional Water Index on a 0-to-1 scale.

Sources

  1. Guidelines for Evaluating Foundation Performance by Monitoring (FPA-SC-12-0) Foundation Performance Association
  2. Guidelines for the Evaluation of Foundation Movement for Residential and Other Low-Rise Buildings (FPA-SC-13-1) Foundation Performance Association
  3. Monitoring And Evaluating Cracks In Masonry U.S. General Services Administration
  4. Tracking Drought Using Soil Moisture Information (BAE-1541) Oklahoma State University Extension
  5. Soil Moisture Oklahoma Mesonet
  6. Foundation Maintenance and Inspection Guide for Residential and Other Low-Rise Buildings (FPA-SC-07-0) Foundation Performance Association
  7. Soil matric suction and active zone depth in Oklahoma Oklahoma State University (ShareOK)

Was this page helpful?