How is a foundation protected from slope creep and creek erosion?
In short: When a house sits near a slope or creek bank, the soil can slowly creep downhill or be carried away by flowing water, undermining the foundation. Stabilization combines grading and drainage to control water, erosion protection and engineered retaining walls 12, and in some cases supports designed for sideways load. This work usually involves a licensed engineer and, for taller walls or floodplain sites, permits 1.
What problems does this address?
Slope creep is slow, downslope movement of soil. Expansive clay swells when wet and shrinks and cracks when dry, and these cycles are not fully reversible 4, which helps loosen and move soil on a slope over time. Signs include tilted retaining walls, fences or trees and cracking concentrated on the downhill side of a house. See slope creep and lateral movement.
Bank erosion happens where a creek or drainage channel cuts into the soil next to a lot, especially during floods. In Oklahoma, major floods frequently occur in spring and fall 3. See erosion, creeks and slopes and creeks and flood history.
The Oklahoma Geological Survey reports that most landslides in the state occur in the eastern third, where the wetter climate and steeper terrain favor them 3.
Why does investigation come first?
A recommended practice for geotechnical work states that on sloped lots where the foundation is closer than four times the slope height to the toe of an embankment, borings should extend at least twice the slope height, and that reports should recommend earthwork stabilization and slope stability requirements 2. Fill on the downhill side of a lot is a common contributor; see fill soils and lot history.
What stabilization methods are used?
Grading and surface drainage
Controlling water is the base of most slope work. Drainage guidelines note that 1:
- Ground next to a foundation should fall 6 inches within the first 10 feet (citing IRC R401.3).
- Bare soil erodes easily and should be covered with sod in the drainage area.
- Swales โ shallow, gently sloped grass channels โ should have a minimum slope of about 0.5%; overly steep swales can erode.
- Water spilling over terrace edges, or roof runoff from eaves without gutters, can erode soil unless the area is protected.
- Gutters are required by the model residential code next to foundations on expansive or collapsible soils, with discharge at least 5 feet from the foundation or into an approved drainage system.
More detail is on drainage solutions and surface drainage and grading.
Retaining walls
A retaining wall holds back soil where the ground level changes. Drainage guidelines describe these points 1:
- A permit is required for walls over 4 feet tall measured from the bottom of the footing, and for any wall supporting a surcharge, regardless of height (IBC/IRC 105.2).
- Walls that may collect water on the uphill side need drainage, such as gravel backfill with drain pipes through the wall or a French drain.
- Dry-stacked block walls typically lean back 7 to 15 degrees; small walls without such features, even 18 to 24 inches tall, can lean outward within a few years.
Bank protection
Along creeks, armoring such as rock (riprap) or wire baskets filled with stone (gabions) is used to resist scour. Work in a mapped floodplain is regulated; flood maps delineate areas with a 1-in-100 chance of flooding in any year 3, and new construction floors in floodplains must be above the base flood elevation 1.
Lateral supports
Standard foundation piers support load vertically. Engineering reviews note that steel pipe piles installed at the wrong angle can lay over or bend under load 5, and soil moving sideways adds forces that vertical piers are not designed for. Sites with active creep are typically designed by an engineer using walls, tiebacks or other elements meant to resist lateral load, with piers addressing only the vertical part. See steel push piers and helical piers.
What are the limitations?
- Usually requires an engineer's design and may require permits 12.
- Cost is driven by wall height and length, access for equipment, the extent of bank protection and engineering and permitting needs.
Related
- Erosion, Creeks and Slopes
- Slope Creep and Lateral Movement
- Drainage Solutions
- Codes and Permits
- Tilted Retaining Walls, Fences or Trees
Common questions
What is slope creep?
Creep is slow downhill movement of soil on a slope. In clay it is pushed along by repeated wetting and drying, and it can tilt fences, retaining walls and trees and pull at the downhill side of a foundation.
Do I need a permit for a retaining wall?
Model building codes require a permit for retaining walls over 4 feet tall, measured from the bottom of the footing to the top of the wall, and for any wall that supports a surcharge such as a building. Local rules can differ.
Can foundation piers stop a house from sliding downhill?
Standard push piers provide vertical support only. Sideways soil movement calls for a design that addresses lateral load, such as engineered walls, tiebacks or other lateral supports.
Where in Oklahoma are landslides most common?
The Oklahoma Geological Survey reports that most landslides occur in the eastern third of the state, where the climate is wetter and the terrain is steeper.
Sources
- Drainage Guidelines (FPA-SC-17-0) Foundation Performance Association
- Recommended Practice for Geotechnical Explorations and Reports (FPA-SC-04-0) Foundation Performance Association
- Geologic Hazards in Oklahoma (GSA South-Central Section abstract) Oklahoma Geological Survey / Geological Society of America
- Chapter C5 โ Expansive Soils Institution of Civil Engineers / British Geological Survey
- Post Foundation Repair Performance of Residential and Other Low-Rise Buildings on Expansive Soils (FPA-RC-01-0) Foundation Performance Association
Was this page helpful?
Thanks. Your note goes straight to the person who maintains this library.